Construction is in full swing

AAA Project Update

Sitework
Construction is in full swing! The site operations are ongoing with the installation of
sewer and gas lines, and earthwork is advancing, including developments on the
stormwater ponds.

Recreation Center
The groundwork is underway. Installation of the stem wall blocks has commenced.
This week, the pool layout will be finalized, and excavation will kick off later on. Next
week will see the start of underground electrical and plumbing work.

Pavilion
The construction of the layout and footings will commence shortly. Over the next few
weeks, the rough-in work beneath the pavilion slab is planned. The pre-engineered
metal structure for the pavilion is expected to ship on March 31st.

These are exiting times on campus where residents are Always Active At Moosehaven!